In order to get the answers to questions you will have during your pool build, we have created this page to let you know who to contact for questions pertaining to your inground pool installation project from Blue Hawaiian Pools of Michigan. Use the buttons below to contact each department by phone.

SALES

Initial Appointment

Pricing

Contract Development

Permit Drawings

Permit Acquisitions

First Day of Install Meeting

Addendums

*Your salesperson will hand off the project on the day of installation to our Installation Crew

INSTALLATION

Open Hole Placement ( Initial Pool Layout )

Fiberglass Shell Placement

Concrete Footing ( for Steel-Wall Vinyl Pools )

Steel Wall Construction

Plumbing

Pump, Filter, Motor ( Initial Installation )

Retaining Walls

Transportation

SERVICE

Power Covers

Vinyl Liner Installation

Filter, Motors, Pumps

Lighting & Water Features

Pool School

Pool Opening

Pool Closing

ADMINISTRATIVE/SCHEDULING

Scheduling is an important part of your pool build. Coordinating multiple industries, townships, and cities in a cohesive manner in order to facilitate the most effective schedule is a task left to our experienced Master Pool Builder & Scheduler.

All Contractors

Concrete

Electrical

Mechanical ( GAS )

Fencing

Stone

Any Questions During Installation

What To Expect During Installation

Week 1

Installation 1-5 Days

Pool Install

Layout Pool, Pour Equipment Pad, Equipment Plumbing, Open Hole, Open Inspection, Install Pool, Backfill

Week 2

Electrical Install

Electrical 3-5 Days

Electrical Installation, Bonding Wire, Electrical Board, Inspection ( inspection takes 1-3 days and varies based on township )

Week 3

Mechanical Install

Mechanical 3-5 Days

Gas line installation is performed after electrical inspection

Week 4

Concrete 12 Days

Concrete Installation

The concrete pour is typically 1-2 days. Our concrete specialist will call to set up the concrete pour – if your pool has to have a “double pour” then this time frame will be extended.

Week 5

Fencing 1-2 Days

Fencing Installation

Your fencing will be installed and ready to use within 1-2 days. Please be sure that you have latch alarms, window alarms, and door alarms where needed so that we can schedule your Final Inspection.

Week 6

Pool School Final Day!

Pool School

At Pool School you will be shown how to use automation, pump, and cleaning tools – we will go over any systems questions you may have and collect the remaining balance of your pool installation.